Case Study - Ince Biomass Power – 2018
Four Packaged Substations & MCC’s for new 22MW Biomass Power Station at Ince, Chester - Total Project Value – £600,000
Packaged Substations incorporated Cast Resin 11kV/400V Transformers with built-in Temperature Monitoring, ACB Incomers, Feeders, Variable Speed Drives and Motor Starters incorporating Rockwell E300 Intelligent Modules with Door Keypads.
Customer MBV (MWH Treatment/Black & Veatch joint venture)
Project Delivery – All four panels were designed, manufactured, tested & installed at site within a 16 week program.